With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (2025)

Edmonton

Fort McMurray sits at the junction of two rivers, which makes it susceptible to ice jam floods in the spring. It experienced a large ice jam flood in 2020. Now, Fort McMurray has extensive infrastructure to prevent a repeat — and is building more.

Located where two rivers meet, Alberta community is vulnerable to ice jams and floods

With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (1)

Dennis Kovtun · CBC News

·

With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (2)

Ever since the devastating spring floods of 2020 in Fort McMurray, the northeastern Alberta community has been shoring up its defences against rising rivers.

Now, officials with the Regional Municipality of Wood Buffalo (RMWB) say Fort McMurray is better prepared for future floods.

"From a permanent structural mitigation standpoint, there's been significant works completed," said James Semple, manager ofRMWB's project management office.

It has spent $119 million on flood mitigation so far; the remaining work that isplanned will bring the total expenditure to about $270 million, according to a statement on the RMWB's website.

  • VideoMilitary assistance requested as flooding hits downtown Fort McMurray

Semple said the aim is to preparethe community for another one-in-100-year flood— which is what Fort McMurray experienced in 2020— as well as aone-in-200-year flood, in which the riverwould rise by another half-metre or so.

Preparation means damages to residents and businesses would beappropriately mitigated, he said.

Vulnerable location

Fort McMurray sits at the confluence of the Athabasca and Clearwater rivers. When ice on these two rivers breaks up in the spring, it can create literal dams in the river. As water backs up, it eventually overflows the banks and can flood low-lying parts of town.

Ice jams tend to form downstream of Fort McMurray, where the Athabasca changes shape, said Nadia Kovachis, a river hydraulics and ice engineer with Alberta River Forecast Centre.

"The river really flattens out, which encourages sediment deposition, and this causes the river to be wider, with many more sandbars and islands. And these things kind of all work together to encourage ice jam formation," she said.

Fort McMurrayhas a long history of spring floods caused by ice jams on the Athabasca River, with records of extreme incidents going back to 1835. Of 17 notable floods since then, 16 were caused by ice jams.

The 2020 flood was caused by a massive 25-kilometre ice jam on the Athabasca. Water from both rivers spilled into downtown, forced about 12,000 people from their homes and caused more than $520 million in insured damage.

After the 2020 flood, an engineering report found that the municipality's flood mitigation system was incomplete and flawed.

Kovachis said it's difficult to predict when ice jam flooding will happen. That's why the mitigation measures are so important.

More infrastructure being built

In September, the RMWB council approved going ahead with structural mitigation between the Clearwater River and nearby Clearwater Drive. This work is the final phase of permanent flood mitigation efforts for downtown Fort McMurray, the municipality said.

Options for this stretch of work include earth berms and retaining walls, the municipality said. Construction is expected to begin next year.The Heritage Shipyard, which houses a collection of historical vessels that used to navigate the Athabasca River, will be relocated to make space for the infrastructure.

With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (3)

Fort McMurray's flood mitigation system is a combination of berms, walls, "the raising of roads, and a variation of different things," said Semple.

The goal is "to bring [up] the level around the lower townsite and other areas that are susceptible to flood, bring them up to a level where it reduces the risk of flooding."

A man-made berm is made of clay and soil and looks like a hill or barrier, with vegetation growing on it. Semple said a berm could withstand an eight to 10 metres rise in water levels,preventing water from inundating that part of the municipality.

The normal water level in Fort McMurray rivers is about 240 metres above sea level.The 2020 flood saw water level rise to about 250 metres.

WATCH | Inthe spring,ice can jam the rivers, causing floods:

With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (4)

Flood-proofing Fort McMurray

24 hours ago

Duration 2:42

Fort McMurray stands at the confluence of two rivers — Athabasca and Clearwater. During the spring thaw, ice can jam the rivers and flood parts of the city. CBC's Dennis Kovtun explains what Fort McMurray is doing to avoid this.

Another flood mitigation measure is an anti-flood wall, which is prominently visible at the intersection of Gordon Avenue and Riedel Streets. It serves as a walkway for residents.

There are also temporary barriers that look like mini-berms, which are prominent in the Heritage Shipyard area.

  • Berms and sandbags: Fort McMurray spending millions in preparation for flood season
  • Fort McMurray's flood mitigation berm system seriously flawed, report says

Erin Sieger, the RMWB'sdirector of emergency management, said the municipality starts preparing in earnest for a possible flood season in early spring.

"In terms of river break-up season, we start getting ready for that in early March, where we reignite our relationships with the river forecasters and start to talk with stakeholders and partners in the region about what they're doing to prepare and how we can help," she said.

Kovachis said there are"no long-lead indicators" that would help predict the flooding well in advance.

  • Berms and sandbags: Fort McMurray spending millions in preparation for flood season

How much snow is left on the ground — and how quickly it melts — play a key role, she said.

"In 2020, we had a really cold late March and early April," she said.

Then the temperatures rose quickly. The thickness of the snowpack was higher than average, and the ice on the river was thick as well.

"So, all of those things worked together for the severity."

ABOUT THE AUTHOR

With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (5)

Dennis Kovtun

Journalist

Dennis Kovtun is a journalist with CBC based in Fort McMurray, Alta., covering a variety of stories in northern Alberta. He was previously based in Edmonton and Grande Prairie. Reach him at dennis.kovtun@cbc.ca.

    Corrections and clarifications|Submit a news tip|

    Related Stories

    • Fort McMurray, Alta., supportive housing facility fears loss of funding
    • Federal minister apologizes, promises better communication with Fort Chipewyan, Alta.
    • Fort Providence, N.W.T., to get new water treatment plant after reports of diesel smells
    • Minister says Fort Chipewyan, Alta., dock is safe, but Ottawa will further assess
    • This Alberta town has mountains on one side, Calgary on the other — and some big growing pains
    With walls, berms and raised roads, Fort McMurray is working to keep its river from overflowing | CBC News (2025)
    Top Articles
    Latest Posts
    Recommended Articles
    Article information

    Author: Chrissy Homenick

    Last Updated:

    Views: 5954

    Rating: 4.3 / 5 (74 voted)

    Reviews: 81% of readers found this page helpful

    Author information

    Name: Chrissy Homenick

    Birthday: 2001-10-22

    Address: 611 Kuhn Oval, Feltonbury, NY 02783-3818

    Phone: +96619177651654

    Job: Mining Representative

    Hobby: amateur radio, Sculling, Knife making, Gardening, Watching movies, Gunsmithing, Video gaming

    Introduction: My name is Chrissy Homenick, I am a tender, funny, determined, tender, glorious, fancy, enthusiastic person who loves writing and wants to share my knowledge and understanding with you.